DATE
|
DAY OF WEEK
|
TASKS
|
|
August 23, 2008
|
Saturday
|
Stand and brace walls. Load roof trusses.
|
|
September 6, 2008
|
Saturday
|
Recess for Labor Day
|
|
September 13, 2008
|
Saturday
|
Stand roof trusses. Install roof sheathing and wall sheathing.
Cut windows and doors.
|
|
September 20, 2008
|
Saturday
|
Install windows and doors, soffits,
fascia, drip edge.
|
|
September 27, 2008
|
Saturday
|
Begin siding, exterior trim, blocking.
|
|
October 4, 2008
|
Saturday
|
Complete siding, exterior trim. Paint.
|
|
October 11, 2008
|
Saturday
|
Complete paint and punch list. Landscape. Dedication
|
|







|
|
|
House No.
|
Start Date
|
End Date
|
Dedication
|
Comments
|
|
53
|
Feb 16, 2007
|
Mar 2, 2008
|
Mar 2, 2008
|
4515 Solar Lane, Dallas. One of two Homes on the Lawn
built simultaneously. Build days are Sat, Sun, Wed, Thurs for 2 weeks.
|
|
54
|
Feb 16, 2007
|
Mar 2, 2008
|
Mar 2, 2008
|
4554 Solar Lane, Dallas. One of two
Homes on the Lawn built simultaneously.
Build days are Sat, Sun, Wed, Thurs for 2 weeks.
|
|
55
|
Mar 1, 2008
|
Apr 26, 2008
|
May 10,
2008
|
3423 Charolais, Dallas. This
is the first
Breast Cancer Build being constructed by breast cancer
survivors to benefit early breast cancer detection. Build consecutive
Saturdays with March 22 recess for Easter.
|
|
56
|
May 10, 2008
|
May 22, 2008
|
May 24, 2008
|
The 2nd annual WillieBuild in
West Dallas, remembering Willie Tichenor. Build
days are Sat, Sun, Wed, Thurs for 2 weeks.
|
|
57
|
Aug 23, 2008
|
Oct 4, 2008
|
Oct 4, 2008
|
First house of the fall. Site is 4708 J. E. Wiley,
Dallas. Build on 6 Saturdays, taking recess for Labor Day weekend.
|
|
58
|
Oct 18, 2008
|
Nov 22, 2008
|
Nov 22, 2008
|
Last house of the year. Site is 7923 Ivory, Dallas. Build on 6 consecutive
Saturdays. Complete before Thanksgiving
|
|